County offices have new move-in projection

 


COLFAX — Construction on the courthouse continues with a new move-in date set for sometime in August.

Facilities Management Director Brandy Dean said ceiling installation, and floor preparation, and installation on the second floor were to be completed earlier this month.

And by Tuesday, June 28, Dean said crews had hoped to complete ceiling installation in offices and floor preparation and installation on the first floor.

Cleanup is expected to begin by Monday, July 11 on the second floor with full building cleanup by Monday, July 25, Dean said.

Officials hope to start heating and air...